MD Anderson Library Water-Proofing and Roofing Repair Project
Beginning this summer, visitors to University of Houston MD Anderson Library will notice building repair work in progress.
The estimated 12-month project includes water-proofing to begin July 5, and roofing replacement to begin in November. Dates are approximations.
Fencing has been positioned around the MD Anderson Library on three sides and will not affect the main entrance. The loading dock area, as well as emergency egress doors, will not be impacted.
During the course of the project, some noise may be heard inside the Library.
Impact to the Library’s surrounding environment will be minimal. The large magnolia tree at the southeast corner of the building will be protected at all times, and other bordering shrubbery and trees may be removed and replaced at the completion of the project.
Updates to the project will be shared as they become available.